Case Study #123 | Crisis averted: UPS battery install Mitsubishi UPS 2033D 30kVA

masthead-blue-ellipse-top masthead-blue-ellipse
two batteries are connected to each other and one has a caution label on it
ProductMitsubishi UPS 2033D 30kVA
ApplicationManufacturing Data Center
SynopsisNew client hired Nationwide Power to inspect and maintain their Mitsubishi UPS 2033D-30kVA, which provides critical power for an existing data center.
Preliminary ActionsUpon inspection, our Critical Power Professional (CPP™) found a battery cable inside the battery cabinet, where the cable’s lug eyelet had melted due to improper torquing /fastening to the battery insert by the previous service company.

If left in its current condition, the cable could have melted during an outage causing a domino-effect including breaking the string’s integrity, dumping the load, and possible risk of fire.  It could have also caused a ground fault which would have not only dumped the load, but also damaged the UPS.
ResolutionOur CPP™ team is equipped with some basic universal repair parts, and in this case a spare battery cable saved the day and was promptly replaced.  By being prepared, our CPP™ left the battery string in a condition that no longer presented a safety threat and left the UPS in proper working condition.

Ongoing and regular UPS battery inspections are recommended by a qualified Critical Power Professional™.
Root CauseThe damaged battery cable appears to be the result of negligence from the previous service provider.  This should have been identified and repaired in previous inspections and is a basic element of any quality maintenance inspection.
Additional ReadingUPS Battery Preventive Maintenance and Service

UPS Battery Case Study with Poor Maintenance

UPS Batteries with No Preventive Maintenance
a close up of a corroded battery connector

Nationwide Power provides 24/7/365 technical support to ensure that everything operates and transitions successfully before, during, and after any power outage.

We are your critical power infrastructure partner!